Support for project development and services at the waste-to-energy plant
Kochi Waste-to-Energy Plant, India
Iqony Solutions (IQS) served as the owner’s engineer for the new waste-to-energy plant in Kochi, providing project development and pre-contract services:
- Review of existing project documents (e.g., feasibility study, detailed project report, and site study report)
- Review of tender documents (e.g., scope of supply, statement of work)
- Support with the financial evaluation of the tender, negotiations with bidders, and on-site coordination
Project facts
| Installed capacity | 10 MWel |
| Fuel | Municipal solid waste, fuel from waste |
| Technology | Waste heat boiler, gasifier |
| Customer | GJ Eco Power Pvt. Ltd. |
| IQS-Service Period | Ongoing |