Study on Securing the Steam Supply for a Refinery Site

Leuna Refinery Power Plant, Germany

Problem Statement:

  • The study was based on a previous analysis of various implementation options for electricity and steam supply
  • Preferred options were developed in greater detail and evaluated from both technical and economic perspectives
  • Analysis of a new facility with seven boiler systems
  • The conversion of existing facilities to natural gas was examined
  • The primary objective is to reduce CO2 emissions

Project facts

Boiler systems• 4 Water-tube boiler
• 3 Large-water-tube boiler
Steam rails• HD-Steam: 39 bar / 370 °C / max. 120 t/h
• MD-Steam: 18 bar / 260 °C / max. 80 t/h
• ND-Steam: 6 bar / 180 °C / max. 60 t/h
Fuel of the futureErdgas
CustomerIqony GmbH / Total Refinery Central Germany
IQS Service Period06/2020 – 12/2020