Preliminary planning for steam supply
Preliminary planning for the steam supply in Leverkusen, Germany
Construction of two gas-fired steam generators:
- Preliminary planning based on a concept study prepared by Iqony Solutions (IQS) in 2019 for the installation of two new gas-fired boilers
- Project status: Preliminary planning completed
Project facts
| Installed capacity | 1x145 t/h and 1x95 t/h |
| Live steam parameters | 130 bar/560 °C |
| Heat output | 127 MWth and 83 MWth |
| Customer | Currenta GmbH & Co. OHG |
| IQS-Service Period | 03/2020 – 07/2020 |