Electricity supplied from the public grid and process steam via the Kreuznach boiler plant

Michelin Tire Works, Bad Kreuznach, Germany

Objective

Energy-efficient supply of steam and electricity to the tire plants

Solution

Operations management by Iqony, modernization of energy generation

  • 10 MW gas turbine with waste heat boiler,
  • Handover of the operating crew

Results

  • Investment: €10 million
  • Savings: €1 million/year
  • CO2 savings: 7,000 tons/year

Impact

Energy savings, cost reduction, integration of the existing system

 

Project facts

Production 
Electricity72.000 MWh/a
Steam167.000 MWh/a